Application of Repetitive Scheduling Method and Time-Cost Trade-Off for Road Construction Projects

Main Article Content

Tanitchet Doungsoma
Paijit Pawan

Abstract

 


This research aims to study and apply the Repetitive Scheduling Method (RSM) integrated with the Time-Cost Trade-Off method to generate a project planning that is suitable for both duration and cost for two road construction projects. The information on the duration and costs of each activity were collected and analyzed using the RSM and Time-Cost
Trade-Off methods by increasing the number of group workers and equipment or machines in the Controlling Sequence. The results showed that the suitability of the first project was at the project duration of 40 days, compared to the CPM method, reducing the project duration by 39.39%, and reducing the total cost of the project by 5.11%. For the second project, the suitability was at the project duration of 82 days, compared to the CPM method, reducing the project duration by 35.94%, and reducing the total cost of the project by 4.74%. Therefore, this research illustrates the application of the Repetitive Scheduling Method (RSM) integrated with the Time-Cost Trade-Off method that can be applied to projects. The proposed method can effectively reduce the duration and cost of road construction projects.

Article Details

Section
บทความวิจัย

References

Agdas, D., Warne, D. J., Norgaard, J. O., and Masters, F. J. (2018). Utility of Genetic Algorithms for Solving Large-Scale Construction Time-Cost Trade-Off Problems. Journal of Computing in Civil Engineering, 32(1), 1-10, https://doi.org/10.1061/(ASCE)CP.1943-5487.0000718.

Albayrak, G. (2020). Novel Hybrid Method in Time–Cost Trade-Off for Resource-Constrained Construction Projects. Iranian Journal of Science and Technology, 44(1), 1295-1307.

Ammar, M. A. (2013). LOB and CPM Integrated Method for Scheduling Repetitive Projects. Journal of Construction Engineering and Management, 139(1), 44-50.

Bakry, I., Moselhi, O., and Zayed, T. (2014). Optimized Acceleration of Repetitive Construction Projects. Automation in Construction, 39(1), 145-151

Dolabi, H. R. Z., Afshar, A., and Abbasnia, R. (2014). CPM/LOB Scheduling Method for Project Deadline Constraint Satisfaction. Automation in Construction, 48(1), 107-118

Doungsoma, T. (2021). Application of Adaptive Neuro-Fuzzy Inference Systems for Evaluating Time Contingency in Tunnel Construction Project. Sripatum Review of Science and Technology, 13(1), 22-37. (in Thai)

Harris, R. B., and Ioannou, P. G. (1998). Scheduling Projects with Repetitive Activities. Journal of Construction Engineering and Management, 124(4), 269-278.

Hegazy, T., and Kamarah, E. (2022). Schedule Optimization for Scattered Repetitive Projects. Automation in Construction, 133(1), 1-13, https://doi.org/10.1016/j.autcon.2021.104042.

Huang, Y., Zou, X., and Zhang, L. (2016). Genetic Algorithm–Based Method for the Deadline Problem in Repetitive Construction Projects Considering Soft Logic. Journal of Management in Engineering, 32(4), 1-9, https://doi.org/10.1061/(ASCE)ME.1943-5479.0000426.

Ioannou, P. G., and Yang, I. T. (2016). Repetitive scheduling method: Requirements, modeling, and implementation. Journal of Construction Engineering and Management, 142(5), 1-13, https://doi.org/10.1061/(ASCE)CO.1943-7862.0001107.

Jamnongnart, K., and Kusalasai, S. (2019). The Construction of a Housing Project with Repetitive Working Patterns Part 1 Working with Different Schedules Between CPM and RSM. Engineering Journal of Research and Development, 30(4), 45-57. (in Thai)

Kusalasai, S. (2018). Planning Repetitive Construction. Nonthaburi: Matichon Pak Kret. (in Thai)

Olivieri, H., Seppänen, O., Alves, T. D. C. L., Scala, N. M., Schiavone, V., and Liu, M. (2019). Survey Comparing Critical Path Method, Last Planner System, and Location-Based Techniques. Journal of Construction Engineering and Management, 145(12), 1-12, https://doi.org/10.1061/(ASCE)CO.1943-7862.0001644.

Pawan, P., and Lorterapong, P. (2016). A Fuzzy-Based Integrated Framework for Assessing Time Contingency in Construction Projects. Journal of Construction Engineering and Management, 142(3), 1-9, https://doi.org/10.1061/(ASCE)CO.1943-7862.0001073.

Promsiri, A., and Pawan, P. (2018). Lag Time in Project Scheduling Network with respect to Risk Event of Weir Construction. Sripatum Review of Science and Technology, 10(1), 198-210. (in Thai)

Saad, D. A., Masoud, M., and Osman, H. (2021). Multi-Objective Optimization of Lean-based Repetitive Scheduling using Batch and Pull Production. Automation in Construction, 127(1), 1-12, https://doi.org/10.1016/j.autcon.2021.103696.

Zou, X., Fang, S. C., Huang, Y. S., and Zhang, L. H. (2017). Mixed-Integer Linear Programming Approach for Scheduling Repetitive Projects with Time-Cost Trade-Off Consideration. Journal of Computing in Civil Engineering, 31(3), 1-6.