APPLICATION OF STANDARD TIME FOR WATER TANK FOUNDATION INSTALLATION USING DIRECT TIME STUDY
Main Article Content
Abstract
Effective time management is a critical factor for the success of construction projects. The construction of water tank foundation installation is a repetitive, high-volume activity, and establishing a time standard is essential for effective project planning and control. This study provides the standard time of water tank foundation installation, which was conducted through a direct time study of 25 water tank bases at Rajamangala University of Technology Lanna, Doi Saket, Chiang Mai Province. The results indicate that the construction process comprises nine sub-activities, with an average standard time of 401.15 minutes, or approximately 6 hours and 41 minutes at 25 bases. The three most time-consuming activities were site preparation and layout at 68.00 minutes, or approximately 1 hour and 8 minutes, ready-mixed concrete pouring at 62.29 minutes, or approximately 1 hour and 2 minutes, and cutting of DB16 SD40 steel reinforcement at 60.43 minutes, or approximately 1 hour, respectively. Although these specific tasks required considerable time due to their inherent complexity, the measured standard time accurately reflects normal productivity levels. This accuracy is attributed to the highly skilled workforce and favorable weather conditions during the study. Ultimately, the standard time derived from this study can be effectively applied to construction planning, cost estimation, productivity assessment, and process improvement.
Article Details

This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.
The published articles are copyright of the Engineering Journal of Research and Development, The Engineering Institute of Thailand Under H.M. The King's Patronage (EIT).
References
ประเสริฐ ดำรงชัย. การวางแผนงานก่อสร้าง. กรุงเทพฯ: ศูนย์บริหารจัดการวิชาศึกษาทั่วไป มหาวิทยาลัยศรีนครินทรวิโรฒ, 2552.
รัชต์วรรณ กาญจนปัญญาคม. การศึกษางานอุตสาหกรรม. กรุงเทพฯ: สำนักพิมพ์ท้อป, 2553.
Barnes, R.M. Motion and Time Study: Design and Measurement of Work. New York: John Wiley & Sons, 1991.
Prakashbhai, P.S., Ankitkumar, P. and Patel, S. Time and motion study of construction activities in industrial building. International Research Journal of Engineering and Technology, 2020, 7(6), pp. 6583–6593.
Walker, D.H. An investigation into construction time performance. Construction Management and Economics, 1995, 13(3), pp. 263–274.
Kanawaty, G. (ed.) Introduction to Work Study. Geneva: International Labour Organization, 1992.
Groover, M.P. Work Systems and the Methods, Measurement, and Management of Work. Upper Saddle River, NJ: Pearson Prentice Hall, 2007..
Freivalds, A. Niebel's Methods, Standards, and Work Design. New York: McGraw-Hill, 2014.
เจริญทรัพย์ งอยจันทร์ศรี และพิชญ์ สุธีรวรรธนา. สาเหตุของงานบกพร่องในงานก่อสร้าง ต้นทุนในการแก้ไข และแนวทางป้องกันการเกิดซ้ำ: กรณีศึกษางานก่อสร้างโรงแรม 1 แห่ง. In: การประชุมวิชาการวิศวกรรมโยธาแห่งชาติ ครั้งที่ 25, จังหวัดชลบุรี, 15–17 กรกฎาคม 2563. Available from: https://conference.thaince.org/index.php/ncce25/article/view/66
Kazaz, A., Manisali, E. and Ulubeyli, S. Effect of basic motivational factors on construction workforce productivity in Turkey. Journal of Civil Engineering and Management, 2008, 14(2), pp. 95–106. Available from: https://doi.org/10.3846/1392-3730.2008.14.4
Bramble, B.B. and Callahan, M.T. Construction Delay Claims. New York: Aspen Publishers, 2010.
Shuaibu, A. Determination of Labour Outputs for Roof Carcassing, Roof Covering and Painting in the Nigeria Construction Industry. Master Thesis, Ahmadu Bello University, Zaria, Nigeria, 2010.
Fagbenle, O., Joshua, O., Afolabi, A., Ojelabi, R., Fagbenle, O., Fagbenle, A. and Akomolafe, M. Cost management practice of construction firms and its influencing factors: Lessons from southwestern Nigeria. In: Construction Research Congress 2018, 2018, pp. 692–700. Available from: https://ascelibrary.org/doi/abs/10.1061/9780784481271.067
Meszek, W., Rejment, M. and Dziadosz, A. Disturbance analysis and their impact on delays in construction process. In: IOP Conference Series: Materials Science and Engineering, 2019, 603(5), 052002. Available from: https://doi.org/10.1088/1757-899X/603/5/052002
พรศิริ คำหล้า, เจษฎา ยาโสภา, ธัญญารัตน์ ไชยกำบัง, ปิยณัฐ โตอ่อน, รัชฎา แต่งภูเขียว, ณัฐนันท์ อิสสระพงศ์ และ กำธร สารวรรณ. การศึกษาเวลามาตรฐานในกระบวนการผลิตคอนกรีตผสมเสร็จด้วยการจับเวลาโดยตรง. วารสารวิชาการเทคโนโลยีอุตสาหกรรม, 2564, 6(2), pp. 41–51.
Maynard, H.B., Stegemerten, G.J. and Schwab, J.L. Methods-Time Measurement. New York: McGraw-Hill, 1948.
Salvendy, G. (ed.) Handbook of Industrial Engineering: Technology and Operations Management. 3rd ed. New York: John Wiley & Sons, 2001.
ฉันนนรี ชะอุ่ม. ปัจจัยที่มีผลต่อความล่าช้าของงานก่อสร้างในโครงการบ้านจัดสรรระบบสำเร็จรูป. วิทยานิพนธ์ปริญญามหาบัณฑิต, มหาวิทยาลัยบูรพา, 2559.
พีร์นิธิ อักษร. การวิเคราะห์ผลิตภาพในการก่อสร้าง. กรุงเทพฯ: ศูนย์หนังสือแห่งจุฬาลงกรณ์มหาวิทยาลัย, 2565.